ReproLining® 0.5 sole reprofiling device
Art. No.: 60000
Base reprofiling device for repairing the trench base in conjunction with ERGELIT mortars
Further properties
Reprolining 0.5 is an efficient invert rehabilitation process that aims to precisely rehabilitate damaged inverts of sewer pipes. This technique is particularly suitable for the targeted rehabilitation of damaged sewer inverts in non-accessible areas with a diameter of DN 100 to DN 800. Reprolining 0.5 shows its strengths for both circular and egg-shaped profiles. This process is also the ideal preparation for advanced techniques such as the centrifugal casting process or pipe lining. Discover the versatile application possibilities of Reprolining 0.5 for the precise repair of your sewers.
- Very robust construction and reusable
- Most economical solution to restore a soleplate
- Suitable for non-accessible ducts up to DN 800 in circular and egg-shaped profiles
- Preparatory measure for centrifugal casting or pipe lining
- Reprolining 0.5 is a process according to DWA-M 143-17 and corresponds to the displacement process described there
- The WW mortars used are tested and certified in accordance with DIN19573
Special features
- Very easy handling
- From DN 600 mm self-propelled
- High centrifugal energy results in excellent adhesion

Application
- Step 1: Preparation with sewer robot: Use of a modern sewer robot for milling work to remove coarse deposits and protruding nozzles.
- Step 2: Thorough cleaning with high-pressure water: Removal of loose particles, separating agents and deposits by thorough cleaning with high-pressure water.
- Step 3: Removal of standing water: Remove standing water from the pipe by suction or using compressed air.
- Step 4: Installation in the starting shaft: Placement of a shut-off bladder in the previous position in the starting shaft. Closure of the house connections within the section to be rehabilitated with a bladder. If necessary, installation of a wastewater transfer line.
- Step 5: Preparation for reprofiling: Pulling in a traction cable. Connection with the reprofiling device. Careful preparation of the WW ERGELIT mortar in a compulsory mixer.
- Step 6: Applying the ERGELIT mortar: Apply the freshly mixed ERGELIT mortar in front of the reprofiling device. A winch is used to pull the material through the pipe in the direction of flow.
- Step 7: Even distribution of the material: Ensure even distribution of the material in the cavities of the channel base.
- Step 8: Checking the remediation result: Comprehensive camera inspection to check the remediation result.
- Step 9: Pressurizing with waste water: After about 2 hours, depending on the WW ERGELIT mortar used, the reprofiled sewer can be put back into operation.